A new state law in Texas, SB 6, significantly changes how large loads interconnect with and operate within The Electric Reliability Council of Texas (ERCOT) grid. Energy companies developing large data centers, crypto...more
As previously reported, Senator Phil King and Senator Charles Schwertner introduced Texas Senate Bill 6 (SB6) in February 2025. After various amendments and updates, the bill has passed the Texas House and Senate and is now...more
The 2025 Texas Legislature has adopted Senate Bill No. 6, which establishes new requirements applicable to interconnection and operation of large load projects (those over 75 MW demand). As of June 5th, the bill has not been...more
On 12 February 2025, Texas Senate Bill 6 (SB6), authored by Sen. Phil King and Sen. Charles Schwertner, was filed. The low bill number on this indicates it is a priority bill and will likely have momentum. If passed, this...more
On October 21, 2021, the Public Utility Commission of Texas (PUCT) approved a rule that creates requirements for power companies to better prepare for winter weather. The rule stems from the Texas Legislature’s passage of...more
In the aftermath of Winter Storm Uri, the Texas Legislature passed Senate Bill 3, which, among other things, required the Public Utility Commission of Texas (“the Commission”) to adopt certain market-related rules. A key...more