We already knew many Federal Judges weren't deferring to EPA, now the 10th Circuit Court of Appeals isn't deferring to Judges...

Mintz on

Just before the holidays I wrote about three Judges of the Fifth Circuit Court of Appeals who decided, over the Army Corps of Engineers' objection, to apply the Supreme Court's Sackett test for determining whether something...more

Davis Wright Tremaine LLP

What Constitutes a Reasonable Period of Time Under the Suspension-of-Work Clause?

In Granite Construction Company, ASBCA No. 62281 (November 1, 2023), the Armed Services Board of Contract Appeals ("Board") addressed the issue of what constitutes a reasonable period of time to suspend work under the...more

Pillsbury Winthrop Shaw Pittman LLP

ASBCA’s FY 2023 Annual Report: Contractor Appeals Are Way Down but Dispositive Motion Activity Is Way Up

The Armed Services Board of Contract Appeals’ 2023 annual report reveals the lowest number of docketed appeals in 40 years, while at the same time the Board deals with the largest number of motions for summary judgment in...more

Pillsbury Winthrop Shaw Pittman LLP

One Contractor Hurdle Defeated: Federal Circuit Holds That the “Sum Certain” Requirement for CDA Claims is Not Jurisdictional

The U.S. Court of Appeals for the Federal Circuit broke with earlier precedent and held that the sum certain requirement imposed on contractors is not jurisdictional and therefore cannot be grounds for dismissal late in the...more

Perkins Coie

Federal Circuit Holds “Sum Certain” Requirement in Government Contracts Cases Is Nonjurisdictional

Perkins Coie on

Clarifying a significant issue in government contracts litigation against the government, the U.S. Court of Appeals for the Federal Circuit has held that the so-called “sum certain” requirement for Contract Disputes Act (CDA)...more

Mitchell, Williams, Selig, Gates & Woodyard,...

Stormwater Management Fees/Municipality: Federal Appellate Court Addresses Application to U.S. Corps of Engineers Properties

The Federal Circuit (“Court”) addressed an issue arising out of a municipality’s agreement to stormwater fees on federal property. See City of Wilmington v. United States, 68 F.4th 1365 (Fed. Cir. 2023). The question...more

Bradley Arant Boult Cummings LLP

Hell or High Water: Why Contractors Must Understand Contractual Risks

The Armed Services Board of Contract Appeals (“ASBCA”) recently denied a contractor’s claim for additional compensation as the contractor failed to establish its work was constructively suspended or that its contract was...more

Mitchell, Williams, Selig, Gates & Woodyard,...

Operation of Bonnet Carre´ Spillway/National Environmental Policy Act: Federal Appellate Court Addresses Whether Army Corps of...

A group of Mississippi municipalities and associations filed a lawsuit in the United States District Court (S.D. Miss.) against the United States Army Corps of Engineers (“Corps”) for allegedly violating the National...more

Mitchell, Williams, Selig, Gates & Woodyard,...

Lake Access: Arkansas Court of Appeals Addresses Challenge to Fees/Restrictions

The Arkansas Court of Appeals (Division 1)(“ACA”) addressed in a February 1st Opinion a challenge to restrictions by a private entity on the use of a lake. See The AGRED Foundation v. Friends of Lake Erling Association, No....more

ArentFox Schiff

Investigations Newsletters: US Supreme Court Requests Solicitor General's Views in FCA Rule 9(b) Context

ArentFox Schiff on

US Supreme Court Requests Solicitor General’s Views in FCA Rule 9(b) Context - On May 16, 2022, the US Supreme Court requested a brief from the US Solicitor General on the level particularly required by Federal Rule of...more

Holland & Hart LLP

More Uncertainty Ahead – WOTUS, SCOTUS and What it Means for Your Project

Holland & Hart LLP on

Since 2015, jurisdiction under the Clean Water Act (CWA or the Act) has been in a near constant state of flux, creating a challenging regulatory landscape for project developers and the regulatory community. The last few...more

Pillsbury Winthrop Shaw Pittman LLP

ASBCA’s FY 2021 Annual Report Details Informative Statistics that Can Guide Potential Contract Disputes Act Claimants

The “new normal” at the ASBCA has produced some interesting results for contractors to consider as they formulate and advance contract claims. The Board docketed a near record low number of new appeals during FY 2021. ...more

Foley Hoag LLP - Environmental Law

The Sacketts Got Their Day in Court on the Merits; Another Lesson in Being Careful What You Wish For

Last week, in what may or may not be the last round in the ongoing efforts by Michael and Chantell Sackett to build a house on wetlands in Idaho, the 9th Circuit Court of Appeals found that: EPA reasonably determined...more

Mintz

Extra Time For States In Clean Water Act Match Unlikely To End

Mintz on

One of the many things I've never understood about soccer (football in the rest of the world) is that the referee can decide, or not, to add "extra time" at the end of the game to account for what she sees as unusual events. ...more

Foley Hoag LLP - Environmental Law

EPA Withdrawal of Its Proposed Veto of a 404 Permit Is Reviewable — This Should Not Be Earth-shattering News

Last week, the 9th Circuit Court of Appeals ruled that EPA’s decision to withdraw its proposed veto of the Army Corps’ Section 404 permit for the Pebble Mine project in Bristol Bay, Alaska, was subject to judicial review. ...more

Pillsbury Winthrop Shaw Pittman LLP

Federal Circuit Clarifies Bid Protest Stay Timeliness Rules

The U.S. Court of Appeals for the Federal Circuit confirms that a protester seeking to avail itself of the statutory “automatic stay” of performance in connection with a GAO bid protest must file that protest within five days...more

Foley Hoag LLP - Environmental Law

When the Music’s Over, Turn Off the Dakota Access Pipeline

Last week, the District of Columbia Court of Appeals affirmed vacatur of the easement issued to the Dakota Access Pipeline by the Army Corps of Engineers. As I noted last month in connection with the Biden Executive Order...more

Perkins Coie

Court Holds That CEQA Does Not Limit Agencies’ Authority to Impose Mitigation Pursuant to Other Laws

Perkins Coie on

The First District Court of Appeal ruled that CEQA does not constrain an agency’s authority to administer and enforce any other laws, including those authorizing imposition of mitigation requirements. Thus, even after an EIR...more

Bradley Arant Boult Cummings LLP

Enhanced Debriefing End Date Still Unresolved: DOJ Seeks to Overturn “NIKA Technologies”

A few months ago, we wrote about how the U.S. Court of Federal Claims (COFC) had defined when the protest clock starts running for a stay of contract performance pending a bid protest if the Department of  Defense’s (DOD)...more

Foley Hoag LLP - Environmental Law

The 4th Circuit Stays Construction of the Mountain Valley Pipeline — A Lesson in Preventing a Fait Accompli

Earlier this week, the 4th Circuit Court of Appeals stayed construction of the Mountain Valley Pipeline. The Court did so with a two-sentence order stating that an opinion would follow. The order was issued hours after oral...more

Flaster Greenberg PC

Marcellus Shale Update: Delaware River Gas Terminal Decision Pits Law Against Politics

Flaster Greenberg PC on

Later this year, it is likely that the Delaware River Basin Commission (DRBC) will vote on whether to approve a new natural gas export terminal to be located on the Delaware River in Gibbstown, New Jersey, just southeast of...more

Foley Hoag LLP - Environmental Law

Dakota Access Lives to Pump Another Day

On Wednesday, the D.C. Circuit Court of Appeals stayed the injunction requiring the shutdown of the Dakota Access Pipeline.  It’s a victory for the operator, Energy Transfer LP, simply because it lives to fight another day. ...more

Bradley Arant Boult Cummings LLP

Don’t Be Unreasonable: Equitable Adjustment Conditioned on Government Contractor’s Proof of Reasonable Interpretation of Contract

The U.S. Court of Appeals for the Federal Circuit, in U.S. Army Corps of Engineers v. John C. Grimberg Co., Inc., recently reversed an Armed Services Board of Contract Appeals (ASBCA) decision that a federal contractor was...more

Foley Hoag LLP - Environmental Law

It’s Not Looking Good For Nationwide Permit 12

Yesterday, the 9th Circuit Court of Appeals refused the appellants’ request for a partial stay of the injunction recently issued against use of the Army Corps Nationwide Permit 12 for oil and gas pipeline projects...more

Benesch

Controversial District Court Decision Vacating Nationwide Permit 12 and Disrupting Pipeline Industry Appealed to Ninth Circuit

Benesch on

Last week, on May 13, 2020, the Army Corps of Engineers (the “Corps”) and TC Energy filed notices of appeal with the United States Court of Appeals for the Ninth Circuit seeking an immediate stay of the Federal District...more

59 Results
 / 
View per page
Page: of 3

"My best business intelligence, in one easy email…"

Your first step to building a free, personalized, morning email brief covering pertinent authors and topics on JD Supra:
*By using the service, you signify your acceptance of JD Supra's Privacy Policy.
- hide
- hide