Latest Posts › Contract Terms

Share:

Invalid payment claims and notices under construction contracts

A key part of the interim payment process in construction projects is the issuing of payment notices by payee and payer alike. Two recent UK cases demonstrate a strict approach being taken by the courts to the validity of...more

Construction contracts: extensions of time and apportionment of delay

If an extension of time (EOT) clause permits the apportionment of delay, what should be taken into account when apportioning delay? Comments in a recent decision of the Singapore Court of Appeal indicate that a party's...more

Singapore goes its own way on ‘no oral modification’ clauses

Since the Rock Advertising decision of the UK Supreme Court in 2018, 'no oral modification' clauses have generally been strictly enforced. However, in Lim v Hong, the Singapore Court of Appeal has set a more flexible test for...more

Oral variations: "My word is my bond"?

Variation powers under construction contracts typically contemplate work being authorised as a variation where it is instructed in writing. This can give rise to disputes over whether work is a "variation" if it is instructed...more

Construction contracts: who bears the risk of cost overruns?

Construction contracts may be priced in a number of ways. For most contracts, even those which are "fixed price", there is usually scope for cost/price variability. Four cases from December 2020 highlight some of the...more

Time bar notices: specifying the contractual basis of claim

Can a valid claim notice issued, on time, referring to one contractual basis, be relied upon where a claim is ultimately pursued on a different ground? In the first authoritative case to consider this issue, the Hong Kong...more

Compelling the performance of construction works

Courts and arbitral tribunals in many jurisdictions have the power to order contractors to perform building works - to order "specific performance" of a construction contract.  But these powers are rarely exercised.  A recent...more

Employer’s right to damages during defects notification period

In a recent case the Singapore Court of Appeal upheld a decision that an employer may recover damages for rectifying defects even when it has not given the contractor the opportunity of doing so during the defects...more

Claims For Liquidated Damages Against Subcontractors

Main contractors often make claims against subcontractors for liquidated damages for delay. A question that sometimes arises is whether liquidated damages may be claimed by a main contractor where there is no corresponding...more

Advance payment guarantees: three unsuccessful attempts to prevent encashment

Advance payment guarantees are commonly used in the construction industry. However, successful challenges to a demand made under an advance payment guarantee appear to be less common. This article looks at three recent cases...more

Offshore wind projects: delays during construction

The offshore wind sector continues to grow at an unprecedented rate, particularly in Europe, and increasingly in Asia and North America. The construction phase of any project is vulnerable to delay. That is particularly the...more

Liquidated damages and penalties in Singapore

Liquidated damages provisions in contracts are unenforceable if they constitute a "penalty". The past few years have seen subtle but important shifts in how the concept of a penalty is defined. A recent decision from the...more

PFI: benchmarking and market testing, a cause of conflict in the long run?

The ongoing Scottish case of Serco Limited v Forth Health Limited highlights the difficulties that can arise when applying benchmarking and market testing provisions in long-term maintenance and service...more

Construction contracts: ambiguities in remeasurement provisions

Remeasurement provisions are commonly used in construction and engineering contracts where there is uncertainty as to the quantity of work to be performed by the contractor. Remeasurement may be desirable in these situations,...more

Shifting foundations: amendments to ground conditions clauses

Amending standard forms of construction and engineering contracts to change the risk level between the parties is a perennial issue. This, however, can lead to disputes due to amendments not clearly reflecting the intention...more

Construction contracts: vesting of title to goods

When does title to goods transfer from a contractor to an employer? This can be a critical issue, especially when a party to a project has become insolvent. A recent English case considered this issue, and the application of...more

Disputes between members of a construction joint venture

The case of Doosan Enpure Limited v Interserve Construction Limited represents a rare consideration by the English High Court of a dispute between members of a construction joint venture. The court found that Interserve was...more

Security of payment: claiming a sum that “may” be due?

A recent decision by Singapore's highest court has held that a contractor must first establish that it is entitled to payment under the contract in order to claim progress payments under the Security of Payment Act, raising...more

When Do Defects Prevent Practical Completion?

Practical completion represents the physical completion of works on construction projects. Despite its importance, it is not a legal term of art, and whether or not practical completion has been achieved requires...more

Striking out total cost claims

A "global" or "total cost" claim is one in which the damages calculation is derived from the total cost of the work incurred by a contractor, minus the bid amount. Such claims are increasingly used by contractors where...more

Liquidated damages in energy projects

In a noteworthy decision to participants in the energy industry, the High Court of England & Wales examined what constitutes a valid liquidated damages clause in the event of delayed completion of a solar project. And last...more

21 Results
 / 
View per page
Page: of 1

"My best business intelligence, in one easy email…"

Your first step to building a free, personalized, morning email brief covering pertinent authors and topics on JD Supra:
*By using the service, you signify your acceptance of JD Supra's Privacy Policy.
- hide
- hide