News & Analysis as of

Government Contracting General Business Civil Procedure

Read Government Contracting Law updates, articles, and legal commentary from leading lawyers and law firms:

Federal District Court in Virginia Holds That Prime Contractor’s Payment Bond Surety Cannot Rely on No-Damages-For-Delay Clause in...

by Pepper Hamilton LLP on

United States v. John C. Grimberg Co., Case No. 1:16-cv-991, 2017 U.S. Dist. LEXIS 173362 (E.D. Virginia, October 19, 2017) - John C. Grimberg (“Prime Contractor”) was awarded a contract (the “Prime Contract”) to design...more

DOJ Should Dismiss Meritless False Claims Act Qui Tam Relator Claims

by Jones Day on

The Situation: Despite recently acknowledging the significant burden imposed by frivolous False Claims Act claims and affirming its statutory grant of power to dismiss meritless claims brought by relators, DOJ has maintained...more

What the DOJ’s Potential Policy Shift on Qui Tam Actions May Mean for Businesses

by Polsinelli on

In a surprise announcement, the Department of Justice (DOJ) announced that the government will move to dismiss a qui tam action brought under the False Claims Act when it determines that the case has no merit. ...more

Michigan Court Of Appeals Holds That Contractor Who Failed To Timely Seek A Time Extension Is Barred From Contesting Liquidated...

by Pepper Hamilton LLP on

Abhe & Svboda, Inc. v. State of Michigan Department of Transportation, 2017 Mich. App. Lexis 1387 (August 29, 2017) - Contractor Abhe & Svboda, Inc. (“A&B”) entered into a contract with the Michigan Department of...more

For Government Contractors: Unsigned Claim Certification Is an Incurable Defect

In September, the Armed Services Board of Contract Appeals (ASBCA) addressed the certification requirements under the Contract Disputes Act (CDA). A motion to dismiss by the U.S. Government prompted the ASBCA to consider...more

Federal Court Holds That Under Louisiana Law, Actual Notice Of Cause Of Delay Satisfies Contractual Notice Requirement Despite...

by Pepper Hamilton LLP on

Parkcrest Builders, LLC v. Hous. Auth. of New Orleans, 2017 U.S. Dist. LEXIS 125012 (E.D. La. August 8, 2017) - The Housing Authority of New Orleans (“the Authority”) contracted with Parkcrest Builders, LLC (“Parkcrest”)...more

September 2017 Bid Protest Roundup

This roundup of notable bid protest decisions issued in September 2017 highlights three decisions, two at the Government Accountability Office (GAO) and one at the Court of Federal Claims (COFC). The first reminds us of the...more

Eighth Circuit Holds That A Motion To Dismiss Based On An Arbitration Clause Is Not A Challenge To The Court’s Jurisdiction

by Carlton Fields on

A municipality sued the company that constructed its water treatment facility, in connection with contaminants found in the water supply. The parties had entered into a series of agreements which contained choice of law and...more

The Supreme Court - October 2, 2017

by Dorsey & Whitney LLP on

On Thursday, September 28, 2017, the Supreme Court granted certiorari in the following cases: Janus v. American Federation, No. 16-1466: Should Abood v. Detroit Board of Education, 431 U.S. 209 (1977), which held that it...more

The Consequences of Failing to Exhaust Administrative Remedies Prior To Filing Suit - Construction and Procurement Law News, Q3...

The Fourth Circuit Court of Appeals, the federal appeals court covering Maryland, Virginia, West Virginia, North Carolina, and South Carolina, affirmed the trial court’s decision to dismiss a contractor’s breach of contract...more

Ninth Circuit Denies Arbitration in a False Claims Act Case

On September 11, 2017, the Ninth Circuit in US and State of Nevada ex rel. Welch v. My Left Foot Children’s Therapy, LLC, upheld the denial of the defendant’s motion to compel arbitration in a False Claims Act (FCA) relator...more

Omaha Breach: Doctrine of First Breach May Hinge on Correct Contract Interpretation

Which party first breached a contract often plays a determinative role in assessing entitlement for damages in a contract dispute. This theory is often referred to as the First or Material Breach Doctrine....more

August 2017 Protest Roundup

There is no question that procurement regulations give agencies significant discretion at every step of the procurement process, and protesters often have a hard row to hoe to overcome the agency’s exercise of that...more

Procedurally Non-Protestable Issues (Post-Award Protest Primer #7)

Before diving into the various protest grounds that may result in a sustained protest at the GAO, let’s look at some sure losers. These are issues that are not protestable and would likely result in a quick dismissal. This...more

D.C. Federal Court Declines to Enjoin Arbitration Because the Arbitrator Could Issue Any Equitable Relief Required, the Integrity...

by Pepper Hamilton LLP on

TK Servs., Inc. v. RWD Consulting, LLC, 2017 U.S. Dist. Lexis 97239 (D.D.C., June 23, 2017) - This litigation arose from a dispute between TK Services, Inc. (“TKS”), as sub-subcontractor, and RWD Consulting, LLC (“RWD”),...more

Judicial acceptance of the SCL Delay and Disruption Protocol 2nd Edition

by White & Case LLP on

The recent Australian case of Santos Ltd v Fluor Australia Pty Ltd [2017] QSC 153 gives credence to the Society of Construction Law Delay & Disruption Protocol 2nd ed in determining the sufficiency of the plaintiff’s pleaded...more

Cross claims, counterclaims and set-offs from another construction contract - Permissible in an adjudication?

by Dentons on

It is commonplace in our local building and construction market for the same parties to enter into multiple contracts for different projects. However, what happens if a main contractor has valid backcharges under Project A...more

Pay Attention to Your Surroundings: Contractor Denied Recovery for Differing Site Conditions Where Condition was Well-Known in the...

The Civilian Board of Contract Appeals (“Board”), the court with jurisdiction over the General Services Administration and other non-defense executive agencies, denied a contractor’s claim for increased labor and equipment...more

Ohio Appeals Court Holds That Contractor Who Seeks Application of HOOP Formula to Calculate Home Office Overhead Need Not Prove...

by Pepper Hamilton LLP on

Wood Elec., Inc. v. Ohio Facilities Constr. Comm’n, 10th Dist. Franklin No. 16AP-643, 2017-Ohio-2743, 2017 Ohio App. Lexis 1745 (May 9, 2017) - The Ohio Facilities Construction Commission (“OFCC”), together with a school...more

A strict enforcement of time bar provisions

by White & Case LLP on

Time bar provisions are a relatively common feature of construction contracts, but often arouse concern because they are seen to be "harsh". A recent case from Northern Ireland confirms that notwithstanding any "harsh"...more

Owners Beware: Washington Appellate Court Holds Playing ‘Gotcha’ With Project Submittal Review Could Breach the Duty of Good Faith...

by Pepper Hamilton LLP on

Nova Contr., Inc. v. City of Olympia, No. 48644-0-II, 2017 Wash. App. LEXIS 913 (Ct. App. Apr. 18, 2017) - This case arose out of a public project in which the City of Olympia (“City”) hired Nova Contracting, Inc. (“Nova”)...more

Interpreting clause 10.1 of the NEC to escape a time bar clause

by Dentons on

Relying on the role of “mutual trust”, “co-operation” and “good faith” to permit fair and equitable judgments is dangerous. It leads to uncertainty and opens the floodgates to pointless litigation....more

California Supreme Court Finds that When it Comes to Intentional Interference Claims, Public Works Projects are Just Different,...

Earlier, we reported on a California Court of Appeals decision – Roy Allan Slurry Seal, Inc. v. American Asphalt South, Inc. – which held for the first time that a second-place bidder on a public works contract could sue a...more

Western Pennsylvania Hospital Stark/Whistleblower/False Claims Case Provides Real World Guidance For Medical Directors’ Contracts

by Tucker Arensberg, P.C. on

Emanuele v. Medicor Associates, was presented to the United States District Court for the Western District of Pennsylvania as cross motions for summary judgment, and provides some guidance regarding the Stark requirements for...more

Federal Court in Alabama Rules that 1999 Amendment to the Miller Act Does Not Preclude Arbitration of Underlying Claims

by Pepper Hamilton LLP on

United States v. Int’l Fid. Ins. Co., No. 16-0472-WS-C, 2017 U.S. Dist. LEXIS 16791 (S.D. Ala. Feb. 7, 2017) - This action arose out of a payment dispute between Bay South Limited, Inc. (“Bay South”) and Stephens...more

167 Results
|
View per page
Page: of 7
Cybersecurity

Follow Government Contracting Updates on:

"My best business intelligence,
in one easy email…"

Your first step to building a free, personalized, morning email brief covering pertinent authors and topics on JD Supra:
Sign up using*

Already signed up? Log in here

*By using the service, you signify your acceptance of JD Supra's Privacy Policy.
*With LinkedIn, you don't need to create a separate login to manage your free JD Supra account, and we can make suggestions based on your needs and interests. We will not post anything on LinkedIn in your name. Or, sign up using your email address.