Bid Protest Minute: Insufficient Funds are Grounds to Cancel

Bass, Berry & Sims PLC on

On April 29, the Government Accountability Office (GAO) denied Davenergy-VCI JV, LLC’s protest of a solicitation’s cancellation, holding that the lack of available funding is sufficient grounds to cancel. In denying the...more

Pillsbury - Bid Protest Debrief

No Funding, No Award: GAO Upholds Corps’ Late-Stage Solicitation Cancellation

In Davenergy-VCI JV, LLC, B-423332, April 29, 2025​, Davenergy-VCI protested the cancellation by the Army Corps of Engineers (Corps) of a solicitation for architectural engineering construction management services for medical...more

Mitchell, Williams, Selig, Gates & Woodyard,...

Army Corps of Engineers/Geographic Distribution of Construction Funding for Water Resources Projects: February 20th U.S....

The United States Government Accountability Office (“GAO”) published a February 20th report titled: Army Corps of Engineers: Geographic Distribution of Construction Funding for Water Resources Projects (“Report”)....more

Mitchell, Williams, Selig, Gates & Woodyard,...

U.S. Government Accountability Office Report: Army Corps of Engineers/Expedited Permitting Process Would Benefit from More...

The United States Government Accountability Office (“GAO”)  issued a January 9th report titled: Army Corps of Engineers: Expedited Permitting Process Would Benefit from More Transparency (“Report”)....more

Bradley Arant Boult Cummings LLP

GAO Sustains Protest Challenging Decision to Convert Competitive Bid Solicitation to Negotiated Procurement

In January 2023, the U.S. Army Corps of Engineers (USACE) issued an invitation for bids (IFB) for a dune and berm replenishment and renovation project along the New Jersey coast. The USACE received two sealed bids for the...more

Fox Rothschild LLP

COFC Says GAO has been wrong on Photocopied Bid Bond Signatures for Decades

Fox Rothschild LLP on

Late last year, the Court of Federal Claims (“COFC”) contradicted long-standing Government Accountability Office (“GAO”) precedent on the acceptability of photocopied signatures on bid bonds finding that the Government’s...more

Buchalter

Contract Void Ab Initio: Key Insights into the KBR vs. Corps of Engineers Affirmative Defense

Buchalter on

In a recent Board decision dated December 13, 2023, the United States Army Corps of Engineers sought to amend its answer in the case of APPEALS OF – KELLOGG BROWN & ROOT SERVICES, INC., under Contract No. W912GB-13-C-0011....more

Morrison & Foerster LLP - Government...

December 2023 Bid Protest Roundup: Supplementation, Conversion, Rejection

This month’s Bid Protest Roundup include decisions regarding supplementation of the record and whether an agency may convert a sealed bid opportunity into a negotiated procurement due to lack of funds, as well as a case in...more

Bass, Berry & Sims PLC

Bid Protest Win for AM General on Multi-Billion Dollar Contract

Bass, Berry & Sims PLC on

We represented AM General (AMG), an automotive manufacturer that builds military vehicles for government customers, including the Humvee, in a successful bid protest involving a $9.7 billion contract for the U.S. Army to...more

Cozen O'Connor

Whose Standing Now? Federal Circuit Changes Jurisdiction Precedent for Bid Protests

Cozen O'Connor on

On Monday, May 22, 2023, the U.S. Court of Appeals for the Federal Circuit (Federal Circuit) issued its decision in M.R. Pittman Group, LLC v. United States, Case No. 21-2325, in which it overturned years of precedent...more

Willcox & Savage

Read Your RFP Carefully. Then Read it Again.

Willcox & Savage on

In the world of federal contracting, one thing is clear. When crafting a response to a Federal Government Request for Proposal (RFP), one must comply with the precise evaluation criteria contained in that document. Failure to...more

Morrison & Foerster LLP - Government...

March 2023 Bid Protest Roundup: Review, Self-Certification

This month's bid protest spotlight considers two recent protests. J.E. McAmis Inc. v. U.S. is an important decision by the U.S. Court of Federal Claims concerning the court's lack of authority to review the U.S. Small...more

PilieroMazza PLLC

Weekly Update for Government Contractors and Commercial Businesses – December 2022

PilieroMazza PLLC on

GOVERNMENT CONTRACTS - 2022 GAO Bid Protest Annual Report: Key Takeaways for Government Contractors - The Government Accountability Office (GAO) recently released its 2022 Bid Protest Annual Report (Report), which...more

Jenner & Block

Government Contracts Legal Round-Up - October 2022 Issue 20

Jenner & Block on

Welcome to Jenner & Block’s Government Contracts Legal Round‑Up, a biweekly update on important government contracts developments. This update offers brief summaries of key developments for government contracts legal,...more

Jenner & Block

Government Contracts Legal Round-Up | 2022 Issue 9

Jenner & Block on

Welcome to Jenner & Block’s Government Contracts Legal Round‑Up, a biweekly update on important government contracts developments. This update offers brief summaries of key developments for government contracts legal,...more

Cohen Seglias Pallas Greenhall & Furman PC

When Exactly Did My Debriefing End?

The GAO’s recent decision in K&K Industries, Inc. reinforces for disappointed offerors that once the government unequivocally states that a debriefing has concluded, the clock has started ticking on the time to file a...more

Pillsbury Winthrop Shaw Pittman LLP

Federal Circuit Clarifies Bid Protest Stay Timeliness Rules

The U.S. Court of Appeals for the Federal Circuit confirms that a protester seeking to avail itself of the statutory “automatic stay” of performance in connection with a GAO bid protest must file that protest within five days...more

Bradley Arant Boult Cummings LLP

Enhanced Debriefing End Date Still Unresolved: DOJ Seeks to Overturn “NIKA Technologies”

A few months ago, we wrote about how the U.S. Court of Federal Claims (COFC) had defined when the protest clock starts running for a stay of contract performance pending a bid protest if the Department of  Defense’s (DOD)...more

Pillsbury Winthrop Shaw Pittman LLP

COFC Provides Bid Protest Timeliness Guidance

In a recent decision, the U.S. Court of Federal Claims (COFC) addressed the timeliness rules for enhanced debriefing situations. The clock for purposes of obtaining an automatic stay and timeliness may start after the...more

Mitchell, Williams, Selig, Gates & Woodyard,...

Environmental/Remediation and Munitions Response Services: U.S. GAO Addresses Protest of U.S. Corps of Engineers Bid Decision

The United States Government Accountability Office (“GAO”) issued a January 16th decision addressing a protest of a United States Corps of Engineers (“Corps”) rejection of a bid proposal. See Matter of Bristol...more

Bradley Arant Boult Cummings LLP

The 3 Most Important Bid Protest Decisions Of 2018 - Law360

In 2018, three particularly important decisions were issued that will have a significant impact on bid protest law for years to come: Dell Federal Systems LP v. United States, PDS Consultants Inc. v. United States, and Oracle...more

Bradley Arant Boult Cummings LLP

GAO Sustains Bid Protest Where, Among Other Things, the Agency Improperly Considered Cost Risk under Its Technical Evaluation

Recently, the Government Accountability Office (GAO) sustained a bid protest involving the U.S. Army Corps of Engineers’ (USACE) evaluation of proposals for remedial action and surface support assistance at the Gilt Edge Mine...more

Snell & Wilmer

Waters of the U.S. Rule Drowning to Start 2016

Snell & Wilmer on

Although likely to survive a presidential veto of a joint resolution seeking to nullify the June 29, 2015 rule submitted by the U.S. Environmental Protection Agency and the U.S. Army Corps of Engineers amending the definition...more

McGuireWoods LLP

No Good News for Small Businesses in Recent GAO Decision

McGuireWoods LLP on

The Government Accountability Office (GAO) recently released a decision in the matter of FedServ-RBS JV, LLC, B-411790, October 26, 2015, that offers little assurance for small companies seeking to form SBA-approved joint...more

Pillsbury Winthrop Shaw Pittman LLP

Corrective Action Catch 22: Court of Federal Claims Holds Agency Action Must Be Rational Even If GAO Protest Decision Was Not.

The United States Court of Federal Claims’ July 15, 2014 decision in RUSH Construction, Inc. v. United States, reflects the unusual circumstance in which the court effectively sat in appellate review of an earlier bid protest...more

25 Results
 / 
View per page
Page: of 1

"My best business intelligence, in one easy email…"

Your first step to building a free, personalized, morning email brief covering pertinent authors and topics on JD Supra:
*By using the service, you signify your acceptance of JD Supra's Privacy Policy.
- hide
- hide