News & Analysis as of

Alternative Dispute Resolution (ADR) Construction Civil Procedure

Read Alternative Dispute Resolution updates, alerts, news, and commentary from leading lawyers and law firms:

Is it wrong to confuse an arbitrator's failure to give reasons with the conduct of proceedings?

by Dentons on

Construction disputes in South Africa are typically subject to dispute resolution by arbitration. This is usually regulated by the Arbitration Act (the Act). Under the common law and section 28 of the Act, an arbitration...more

Appellate Court Holds That The New Mexico Unfair Practices Act Applies To A “Services” Contract For The Construction Of A Home,...

by Pepper Hamilton LLP on

Fogelson v. Bozzone, 2017 N.M. App. LEXIS 58 (July 26, 2017) - In May of 2008, Wallen Development, LLC (“Wallen”) entered into a written agreement to construct and sell a new home to David and Corinne Fogelson...more

Eighth Circuit Holds That A Motion To Dismiss Based On An Arbitration Clause Is Not A Challenge To The Court’s Jurisdiction

by Carlton Fields on

A municipality sued the company that constructed its water treatment facility, in connection with contaminants found in the water supply. The parties had entered into a series of agreements which contained choice of law and...more

A new division within the DIFC Courts, the Technology and Construction Division

by Hogan Lovells on

The DIFC Courts, last week, published Part 56 (Technology and Construction Division) of the Court Rules ("Part 56") marking the launch of the Court's new division - the Technology and Construction Division ("TCD"). This...more

Federal District Court in South Dakota Compels Arbitration Despite Defendant’s Failure to First Submit the Dispute to the Project...

by Pepper Hamilton LLP on

Dlorah, Inc. v. KLE Constr., LLC, No. CIV. 16-5102-JLV, 2017 U.S. Dist. LEXIS 11043 (D.S.D. July 17, 2017) - Plaintiff, Dlorah, Inc. (“Dlorah”), filed suit against defendant, KLE Construction, LLC (“KLE”), in connection...more

Under Construction - September 2017

by Snell & Wilmer on

Welcome to the fall 2017 edition of our Under Construction newsletter. We hope your summer has left you relaxed and refreshed to make the final push to successfully finish out the remainder of the year. In this issue, we...more

D.C. Federal Court Declines to Enjoin Arbitration Because the Arbitrator Could Issue Any Equitable Relief Required, the Integrity...

by Pepper Hamilton LLP on

TK Servs., Inc. v. RWD Consulting, LLC, 2017 U.S. Dist. Lexis 97239 (D.D.C., June 23, 2017) - This litigation arose from a dispute between TK Services, Inc. (“TKS”), as sub-subcontractor, and RWD Consulting, LLC (“RWD”),...more

Michigan Appellate Court Rules That, Absent Proof of Prejudice, Defendant’s Filing of a Cross-Complaint Does Not Constitute a...

by Pepper Hamilton LLP on

Universal Acad. v. Berkshire Dev., 2017 Mich. App. LEXIS 975 (Ct. App. June 20, 2017) - The dispute arose out of an agreement between Universal Academy (“Universal”) and Berkshire Development (“Berkshire”), under which...more

Connecticut Appellate Court Holds That Owner’s Loss in Arbitration to General Contractor on Claims of Defective Work Operates as...

by Pepper Hamilton LLP on

Girolametti v. Michael Horton Assoc., 2017 Conn. App. Lexis 228 (June 6, 2017) - A General Contractor brought claims for unpaid added work, via mandatory arbitration, against a building owner who asserted defective work...more

JAMS Global Construction Solutions Newsletter, Summer 2017

by JAMS on

Expedited Construction Adjudication: A Better Process for Resolution of Performance Bond Disputes - For the sake of the parties and the construction project, it would be ideal if major contested construction disputes,...more

Court Rejects Claim That Arbitrator’s Ruling Was In Manifest Disregard Of The Law

by Carlton Fields on

A court has granted a petition to confirm an arbitration award despite the defendant’s argument that the arbitrator acted in manifest disregard of the law. While acknowledging questions regarding the continuing viability of...more

Second Circuit Finds Arbitrator Did Not Commit A Manifest Disregard Of The Law In Dispute Over Construction Work At The Whitestone...

by Carlton Fields on

In a dispute between a construction company hired by New York State to replace a portion of the Whitestone Bridge and a steel company regarding the timeliness of certain deliveries related to the project, the Second Circuit...more

DIFC Courts propose specialist Technology and Construction Division

by White & Case LLP on

DIFC Courts seek public consultation for proposed specialist Technology and Construction Division. The DIFC Courts are an important forum for dispute resolution in the Gulf and wider Middle East region. However,...more

District Court Find No Federal Question Jurisdiction In Action Challenging Arbitration Award Based On Arbitrator Bias

by Carlton Fields on

A federal court has rejected the attempt of the losing party in an arbitration to engage in discovery regarding the potential bias of the arbitrator, finding that it had no jurisdiction over the matter because it did not...more

Federal Court in Alabama Rules that 1999 Amendment to the Miller Act Does Not Preclude Arbitration of Underlying Claims

by Pepper Hamilton LLP on

United States v. Int’l Fid. Ins. Co., No. 16-0472-WS-C, 2017 U.S. Dist. LEXIS 16791 (S.D. Ala. Feb. 7, 2017) - This action arose out of a payment dispute between Bay South Limited, Inc. (“Bay South”) and Stephens...more

Adjudication case review: challenging an adjudicator's jurisdiction

by Dentons on

Adjudication case review: recent adjudication enforcement decisions - While disputes referred to adjudication have become increasingly complex, the fundamental principles remain largely unchanged – an adjudicator's...more

Rhode Island Supreme Court Rules That Despite Deference Afforded Arbitrator, the Award Must Be Vacated Where Arbitrator’s Decision...

by Pepper Hamilton LLP on

Nappa Constr. Mgmt., LLC v. Flynn, 2017 R.I. LEXIS 13 (R.I. Jan. 23, 2017) - Caroline and Vincent Flynn (the “Flynns”) contracted with Nappa Construction Management, LLC (“Nappa”) to construct an automobile repair...more

Texas Court of Appeals Holds That the Effect of a Failure to Meet a Specific Contractual Deadline for Arbitration is a Procedural...

by Pepper Hamilton LLP on

Tilson Home Corp. v. Zepeda, No. 14-16-00075-CV, 2016 Tex. App. LEXIS 12022 (Tex. App. Nov. 8, 2016) - The Court of Appeals of Texas has held that an arbitrator—not a trial court—must determine whether a prerequisite to...more

Picerne Construction Corp. v. Castellino Villas (Feb. 18, 2016, C071197)

The Third District Court of Appeal recently held that completion under the mechanics lien statute requires actual completion of the work of improvement, meaning completion of the entire structure or scheme of improvement as a...more

Under Construction - December 2016

by Snell & Wilmer on

Welcome to the winter 2016 edition of our Under Construction newsletter. We hope your year has been good to your family, your company and you as we wrap up these remaining few weeks of 2016. A recent hot topic with...more

Court Grants Default Judgment Confirming Arbitration Award, With A Lesson On Jurisdiction

by Carlton Fields on

Choice Hotels filed an application to confirm an arbitration award of over $247,000 for the alleged breach of a franchise agreement by two defendants, which failed to timely commence construction of a hotel. The defendants...more

Construction Group News: What Happens in Mediation Stays in Mediation

by Murtha Cullina on

The Massachusetts Appeals Court recently held that statements made by a party during mediation cannot be used later in a lawsuit to support a claim of fraud or similar claims. ZVI Construction Co. v. Levy, et al., 90 Mass....more

Nationwide Injunction Issued Against Fair Pay and Safe Workplaces Reporting Requirements and Arbitration Agreement Restrictions

by Holland & Knight LLP on

Late Monday evening, just before the FAR Final Rule and DOL Guidance on the Fair Pay and Safe Workplaces Executive Order (FPSWP) were set to take effect, a federal district judge in Texas enjoined the implementation of the...more

North Carolina Federal Court Holds That Arbitration Clause Requiring Panel To Render A Decision Within 30 Days Is Not...

by Carlton Fields on

In July, a federal court in North Carolina held that an arbitration provision which required the arbitration panel to reach a decision within thirty days of their selection was not unconscionable. Arising out of a dispute...more

Third Circuit Rejects Contractor’s Challenge To Arbitral Jurisdiction Based On Failure To Comply With Agreement’s Procedural...

by Carlton Fields on

The Third Circuit affirmed a lower court’s ruling against a contractor challenging an arbitrator’s authority in ordering payment of delinquent contributions to employee benefit funds. Plaintiff (“Nolt”) signed a Project Labor...more

113 Results
|
View per page
Page: of 5
Cybersecurity

Follow Alternative Dispute Resolution (ADR) Updates on:

"My best business intelligence,
in one easy email…"

Your first step to building a free, personalized, morning email brief covering pertinent authors and topics on JD Supra:
Sign up using*

Already signed up? Log in here

*By using the service, you signify your acceptance of JD Supra's Privacy Policy.
*With LinkedIn, you don't need to create a separate login to manage your free JD Supra account, and we can make suggestions based on your needs and interests. We will not post anything on LinkedIn in your name. Or, sign up using your email address.